CFA Portfolio Management Formula Sheet: Level 1 Edition

Every Level I portfolio calculation comes from one short list: two-asset return and risk, beta, the CAPM E(Ri)=Rf+βi[E(Rm)−Rf]E(R_i) = R_f + \beta_i[E(R_m) - R_f], and Sharpe, Treynor, M² and Jensen's alpha. Portfolio risk is not a weighted average unless ρ = +1.

  • Level I · Portfolio Construction
  • 10 min read
  • Updated

Two-asset portfolio simulator

Set each asset's return and risk, then drag the correlation: the curve of possible mixes bends left as ρ falls, while your mix's return stays put.

Expected return0%10%20%0%5%10%15%Portfolio σYour mixAsset 1Asset 2Efficient frontierInefficient partρ = +1 line
Portfolio return
11.0%
Portfolio σ
14.9%
Risk cut by ρ
3.6%
Min-variance weight, asset 1
87%

At ρ = 0.20, σp is 14.9%, below the 18.5% weighted average. The return, 11.0%, ignores ρ.

Every mix of the two assets at your correlation, against the straight ρ = +1 line

Portfolio Management carries an 8–12% weight on CFA Level 1 (2027 curriculum, where the topic is called Portfolio Construction): roughly 14 to 22 of your 180 questions. Almost every calculation question in the topic comes from a short list of formulas: two-asset return and risk, CAPM, and four performance measures. This CFA portfolio management formula sheet collects all of them in one place.

There is a twist, though. PM is the one Level 1 topic where formulas and graphs are inseparable. The CAL, CML, and SML look alike on a page, and examiners exploit that. So this sheet pairs each formula with the line it draws: what sits on the x-axis, what the slope means, and which assets plot on it.

The target reader: a Level 1 candidate in final review who wants every PM formula stated completely, with the traps flagged. No derivations, no filler.

Portfolio return and risk formulas: two-asset math

The two-asset portfolio is the core computational engine of Level 1 PM. Expected return, variance, covariance, and correlation all show up here, and the variance formula is the single most tested calculation in the topic.

The good news: portfolio return is trivially easy. The bad news: portfolio risk is not a weighted average, and the exam is built around candidates who forget that.

Master the three blocks below and you can answer any two-asset question, including the "what happens to risk when correlation falls" conceptual variants.

Portfolio expected return

E(Rp) = w1 × E(R1) + w2 × E(R2): the weighted average of the individual expected returns, where weights are based on market values and sum to 1.

That is the whole formula. Return is linear in weights, always, regardless of correlation. If a question asks for portfolio return, ignore every standard deviation and correlation number in the vignette: they are distractors.

For more than two assets the logic extends directly: E(Rp) = Σ wi × E(Ri). Weights can be negative if a position is shorted or if the investor borrows at the risk-free rate, which is exactly what happens on the CAL beyond the tangency point.

Two-asset portfolio variance and standard deviation

σp² = w1²σ1² + w2²σ2² + 2 × w1 × w2 × ρ12 × σ1 × σ2, and portfolio standard deviation is the square root of that: σp = √σp².

σp2=w12σ12+w22σ22+2w1w2ρ12σ1σ2\begin{aligned} \sigma_p^2 &= w_1^2\sigma_1^2 + w_2^2\sigma_2^2 \\ &\quad + 2w_1w_2\rho_{12}\sigma_1\sigma_2 \end{aligned}
Take the square root for σp. Given covariance instead, the last term is 2w1w2Cov12.

Note the structure: two squared terms plus one cross term. The cross term uses correlation times both standard deviations, which is just covariance (Cov12 = ρ12σ1σ2), so you will also see the formula written with 2w1w2Cov12 at the end. Same formula, two costumes: learn to recognize both.

Two traps account for most lost points. First, forgetting the 2 in the cross term. Second, reporting variance when the question asks for standard deviation (or vice versa). Answer choices are engineered to catch both errors, so slow down on the final step.

Drag the correlation in the simulator at the top and watch portfolio σ fall

Covariance and correlation

Cov12 = ρ12 × σ1 × σ2, and rearranged, ρ12 = Cov12 / (σ1 × σ2). Correlation is just covariance standardized to the range −1 to +1.

Exam questions routinely give you covariance and ask you to work through the variance formula, or give correlation and expect you to build covariance yourself. Being fluent in both directions is worth easy points. The probability-weighted version of covariance (summing probability times the product of deviations from each mean) connects PM to Quant, and we cover it in the probability formulas sheet.

Interpretation matters as much as computation. Correlation below +1 produces diversification: portfolio risk falls below the weighted average of individual risks. At ρ = +1, and only at ρ = +1, portfolio standard deviation equals the weighted average: the one case with zero diversification benefit.

At ρ = −1, risk can be driven to zero with the right weights. The exam loves the conceptual version: "as correlation decreases, portfolio standard deviation…" Decreases. Every time.

CAPM, beta, and the SML formulas

CAPM is the most-tested single formula in Level 1 Portfolio Management, and it leaks into Corporate Finance (cost of equity) and Equity (required return for valuation). Learn it once, use it in three topics.

This section also carries the graph burden: the SML is the picture of CAPM, and the exam tests whether you know how it differs from the CML. Candidates who memorize the formulas but not the lines get the "which statement is correct" questions wrong.

Here is each formula, followed by the line-by-line comparison that fixes the confusion for good.

The CAPM formula

E(Ri) = Rf + βi × [E(Rm) − Rf]: expected (required) return equals the risk-free rate plus beta times the market risk premium.

E(Ri)=Rf+βi [E(Rm)−Rf]E(R_i) = R_f + \beta_i\,[E(R_m) - R_f]
The bracket is the market risk premium. If a question gives the premium, use it as it is.

The bracketed term, E(Rm) − Rf, is the market risk premium. The most common trap: the question supplies the market risk premium directly, and candidates subtract Rf from it again. Read whether you are given the market return or the market risk premium before you plug in anything.

CAPM's output is a required return. Compare it with your forecast return to make the classic valuation call: forecast above CAPM means the asset plots above the SML and is undervalued (buy); forecast below means overvalued. This same required return feeds the cost of equity in WACC and cost of capital problems.

Beta: two formulas, one number

βi = Cov(Ri, Rm) / σm², or equivalently βi = ρim × σi / σm. Both give the same beta; which one you use depends on what the question hands you.

βi=Cov(Ri,Rm)σm2=ρim σiσm\beta_i = \frac{\text{Cov}(R_i, R_m)}{\sigma_m^2} = \frac{\rho_{im}\,\sigma_i}{\sigma_m}

Beta measures systematic risk only: sensitivity to the market. The market itself has a beta of 1, the risk-free asset a beta of 0. A beta of 1.3 means the stock tends to move 1.3% for every 1% market move.

The conceptual point examiners test: CAPM says only systematic risk is priced. Total risk (σ) includes unsystematic risk, which diversification eliminates for free, so the market pays no premium for bearing it. That single sentence explains why the SML uses beta while the CML uses standard deviation.

CML vs. SML: which line is which

The CML plots expected return against total risk (σ) and holds only efficient portfolios: combinations of the risk-free asset and the market portfolio. The SML plots expected return against beta and holds every correctly priced asset, efficient or not.

Two more contrasts complete the picture. The CML's slope is the market's Sharpe ratio, (E(Rm) − Rf)/σm; the SML's slope is the market risk premium, E(Rm) − Rf. And a poorly diversified stock sits below the CML while sitting exactly on the SML if fairly priced.

Use this checklist when a question shows you a line:

  • X-axis is σ (total risk) → CML (or a CAL). Only efficient portfolios plot on it.
  • X-axis is β (systematic risk) → SML. All fairly priced assets plot on it.
  • Slope = Sharpe ratio of the market → CML.
  • Slope = market risk premium → SML.
  • Asset plots above the SML → undervalued; below → overvalued.

Performance measures: Sharpe, Treynor, Jensen, M-squared

Four risk-adjusted performance measures appear on Level 1, and they split cleanly along the same fault line as the CML/SML: two use total risk, two use beta. Recognize that split and half the conceptual questions answer themselves.

Calculation questions here are quick: each formula is one line. The harder questions ask which measure is appropriate: total-risk measures (Sharpe, M²) suit an investor whose whole wealth is in the portfolio; beta-based measures (Treynor, Jensen's alpha) suit a portfolio that is one well-diversified slice of a larger whole.

The table is the sheet. The subsections below add the details the table cannot hold.

MeasureFormulaRisk usedResult type
Sharpe ratio(Rp − Rf) / σpTotal risk (σ)Slope (ranking only)
M-squared (M²)(Rp − Rf) × (σm/σp) + RfTotal risk (σ)Return in %, compare to Rm
Treynor ratio(Rp − Rf) / βpSystematic risk (β)Slope (ranking only)
Jensen's alphaRp − [Rf + βp × (Rm − Rf)]Systematic risk (β)Return in % above CAPM

Sharpe ratio and M-squared

Sharpe = (Rp − Rf) / σp: excess return per unit of total risk. It is literally the slope of the CAL through the portfolio; a higher Sharpe means a steeper, better line.

Sharpe's weakness: the number is hard to interpret in isolation. Is 0.6 good? Depends on the market. M² fixes that by restating the same information as a percentage return: M² = (Rp − Rf) × (σm/σp) + Rf. It levers or de-levers the portfolio to match market risk, then reports what it would have earned.

M2=(Rp−Rf) σmσp+RfM^2 = (R_p - R_f)\,\frac{\sigma_m}{\sigma_p} + R_f
Compare it with Rm: M² above Rm beat the market on a total-risk basis.

Compare M² with the market return: M² − Rm positive means the portfolio beat the market on a risk-adjusted, total-risk basis. Because M² is a monotonic transformation of Sharpe, the two always rank portfolios identically: a stated exam point.

The returns you feed these ratios matter too; if a question makes you compute Rp first, the holding-period and time-weighted machinery lives in our return formulas guide.

Treynor ratio and Jensen's alpha

Treynor = (Rp − Rf) / βp: the same excess return, but per unit of systematic risk. Use it when the portfolio is a diversified component of larger wealth, so unsystematic risk is irrelevant.

Jensen's alpha = Rp − [Rf + βp × (Rm − Rf)]: actual return minus the CAPM-required return. It is the vertical distance between the portfolio and the SML: positive alpha plots above the line, negative below. If you can compute CAPM, you can compute alpha; it is one extra subtraction.

Ranking caution for the exam: Sharpe and Treynor can rank the same set of portfolios differently, because a portfolio with heavy unsystematic risk looks worse on Sharpe than on Treynor. A question that shows conflicting rankings is testing exactly this: neither measure is "wrong"; they price different risks.

Utility, indifference curves, and the CAL

The last formula block covers how investors choose along the CAL: the utility function, the capital allocation line equation, and the optimal-portfolio logic that ties them together. Fewer calculations get tested here, but the concepts fill plenty of question stems.

The utility formula: U = E(R) − 0.5 × A × σ², where A is the risk-aversion coefficient. Higher A means a more risk-averse investor who demands more return per unit of variance. A is positive for risk-averse investors, zero for risk-neutral, negative for risk-seekers. Use variance in decimal form (0.04, not 20%²-as-400): units are a classic slip.

The CAL equation: E(Rp) = Rf + σp × [(E(Ri) − Rf) / σi]: a straight line from the risk-free rate with slope equal to the risky portfolio's Sharpe ratio. When the risky portfolio is the market, the CAL becomes the CML. The optimal portfolio for any investor is where their highest attainable indifference curve just touches the CAL: more risk-averse investors (steeper curves) end up closer to Rf, less risk-averse investors further up the line, possibly levered beyond the tangency point.

Watch these recurring slips across the whole PM sheet:

  1. Using the market return where the question gave the market risk premium (or vice versa) in CAPM.
  2. Dropping the 2 in the two-asset variance cross term.
  3. Reporting variance when standard deviation is asked.
  4. Comparing a Sharpe number to a return number: slopes rank, only M² and alpha are percentages.
  5. Putting σ on the SML's x-axis or β on the CML's in graph questions.

If PM formulas are settled and you want the next compact sheet, derivatives payoffs and put-call parity is the natural companion topic.

📌 CTA: This sheet covers one topic of ten. Our Must-Know CFA Exam Formulas e-book packs every Level 1 formula (PM, Quant, FSA, Fixed Income, and the rest) into one printable, exam-tuned PDF. One clean layout, no fluff.

Questions people ask

Three questions dominate what candidates actually search about the PM topic, and they deserve straight answers rather than folklore.

They cover exam weight, memorization strategy, and the perennial CML-versus-SML confusion. Each answer below leads with the direct response, then the reasoning.

As of 28 November 2026, all figures reference the 2027 curriculum and official CFA Institute topic weights.

1How many questions is portfolio management on CFA Level 1?

Portfolio Management is weighted 8–12% on Level 1 (2027 curriculum, where it is called Portfolio Construction; as of 28 November 2026), which translates to roughly 14–22 of the 180 exam questions.

That puts it in the middle band of topics: smaller than Quant, FSA, Equity, and Fixed Income (each 11–14%), larger than Derivatives (6–9%). It is dense in formulas relative to its reading load, which makes it one of the better points-per-study-hour topics.

Expect a mix: perhaps half calculation (variance, CAPM, ratios) and half conceptual (diversification, which measure to use, which line is which). The formula sheet above covers the calculation half completely.

2Do I need to memorize the two-asset portfolio variance formula?

Yes: memorize it cold. It is among the most frequently tested calculations in the topic, and there is no shortcut that avoids it.

The memory hook: it mirrors the algebra of (a + b)² = a² + b² + 2ab, with each term dressed in weights and risks: two squared terms plus a doubled cross term. If you can expand a binomial, you already know the skeleton.

Drill it in both costumes: the version ending in 2w1w2ρ12σ1σ2 (given correlation) and the version ending in 2w1w2Cov12 (given covariance). Questions deliberately supply one input when you rehearsed the other.

3What is the difference between the CML and the SML?

The CML plots return against total risk (σ) and contains only efficient portfolios; the SML plots return against beta and contains every fairly priced asset.

Slopes differ accordingly: the CML's slope is the market Sharpe ratio, (E(Rm) − Rf)/σm, while the SML's slope is the market risk premium, E(Rm) − Rf. The SML is simply CAPM drawn as a line.

Practical test-taking rule: check the x-axis label first. σ means CML, β means SML, and once you know the line, the properties in the checklist earlier in this post follow automatically.