BA II Plus Depreciation Worksheet: SL, DB and SYD Keys

Press 2ND [DEPR], pick the method with 2ND [SET], then key LIF, M01, CST and SAL with ENTER and ↓; DEP, RBV and RDV compute as you scroll past YR. For one straight-line year the formula is faster; the worksheet wins a multi-year DB or SYD schedule.

  • Financial Statement Analysis
  • 11 min read
  • Updated

Depreciation schedule visualizer

Book value at each year-end under all four methods, full years from M01 = 1; the readout follows the method you pick.

Method
DB percent
Book value012345$0$2,000$4,000$6,000$8,000$10,000YearRBV at YRStraight-line, SLDeclining, DBDB with switch, DBXSum of digits, SYD
DEP, the year's expense
$4,000.00
RBV, book value left
$6,000.00
RDV, still to write off
$6,000.00

Pure DB still leaves $777.60 to write off after year 5. DBX closes that gap.

DB and SYD fall fastest in the early years; SL is the straight line they are measured against.

There is a button on your BA II Plus that builds a full depreciation schedule for you, and most candidates go their entire prep without pressing it once. That is not laziness: you can clear Financial Statement Analysis (FSA) knowing straight-line and declining-balance by formula alone, and plenty do. But the DEPR worksheet is quietly one of the fastest tools on the calculator, once the keystrokes stop feeling foreign.

This guide is a keystroke reference for the depreciation ba ii plus worksheet: how to open it, switch methods, the order variables prompt in, and how to read DEP, RBV and RDV for any year. It ends with an honest comparison of worksheet time versus formula time.

Everything below follows the official TI BA II Plus guidebook sequence. The BA II Plus Professional uses the identical DEPR worksheet, so every keystroke applies to both models.

Opening DEPR and choosing the method

Press 2ND [DEPR] to open the worksheet. The display shows the active method: SL by default, or whatever you last used, since the calculator retains worksheet data even when powered off. There's no P/Y, C/Y or BGN/END setting to check here; TVM settings don't apply inside DEPR.

Before entering new numbers, clear leftover data with 2ND [CLR Work]. This resets LIF, CST, SAL and YR without touching the method itself. To change the method too, cycle through options with 2ND [SET] until the one you want appears.

Every value typed into DEPR (cost, salvage, life) is a plain positive number. There's no cash-outflow sign convention here, unlike TVM problems where PV, PMT and FV need consistent negative signs. One rule does matter: Error 2 fires if salvage is entered greater than cost, since an asset can't depreciate below its own salvage value.

The six methods behind 2ND [SET]

Pressing 2ND [SET] repeatedly cycles through six built-in methods. Two (SLF and DBF, the French variants) only appear if the calculator's date or number-separator format is set to European; otherwise the cycle skips them.

For CFA purposes, only three matter: SL, DB and SYD. DBX is a real accounting technique: it runs declining balance until straight-line on the remaining book value produces a bigger deduction, then switches automatically. But it's rarely tested by that name.

Cycling past a method you don't want costs nothing: 2ND [SET] steps to the next option without changing any stored numbers, so scroll through all six freely before settling on the one a problem calls for.

  • SL: straight-line
  • SLF: French straight-line (needs European format)
  • SYD: sum-of-the-years'-digits
  • DB: declining balance, percentage you set
  • DBX: declining balance with automatic crossover to SL
  • DBF: French declining balance (needs European format)

Clearing data and reading the defaults

A subtle trap: switching from DB to SL leaves the DB percentage stored even though SL doesn't use it. It won't error, but switching back to DB later restores that old percentage instead of the 200% default.

Clear work between problems when working several back to back. It costs one keystroke and removes a whole category of "why is my answer wrong" debugging later.

The clear-work defaults are worth memorizing: LIF and YR reset to 1, CST and SAL reset to 0, and the method and DB/DBX percentage stay as they were. If DEP comes out zero, check whether CST silently stayed at 0 because clearing was skipped.

Straight-line: cost, salvage, life, year

Straight-line is the simplest path through the worksheet. Answer-first: the input order is LIF, M01, CST, SAL, YR, and DEP, RBV and RDV then compute automatically as you scroll past YR.

Each entry step ends with ENTER before moving on with the down arrow: the calculator won't store the number otherwise. This is the single most common cause of a wrong DEPR answer on a first attempt.

Worked example from the TI guidebook: a company depreciates a $1,000,000 commercial building starting mid-March, 31.5-year life, no salvage. Keying LIF = 31.5, M01 = 3.5, CST = 1,000,000, leaving SAL and YR at default, gives DEP = $25,132.28, RBV = $974,867.72 and RDV = $974,867.72 for year one.

StepKeysDisplay
12ND [DEPR]current method (SL)
22ND [CLR Work], ↓clears old data
331.5 ENTER, ↓LIF = 31.50
43.5 ENTER, ↓M01 = 3.50
51000000 ENTER, ↓CST = 1,000,000.00
6↓ (leave SAL at 0)SAL = 0.00
7↓ (leave YR at 1)YR = 1.00
8↓DEP = 25,132.28
9↓RBV = 974,867.72
10↓RDV = 974,867.72

Reading M01 correctly

M01 is the field candidates get wrong most, since it packs two numbers into one. Answer-first: the integer part is the month the asset enters service, and the decimal part is how far through that month depreciation begins.

Enter 3.5 for an asset placed in service mid-March. Enter 4.25 for one that begins depreciating a quarter through April (a quarter through the month, not the 25th). This is why year one above was $25,132.28 rather than the full-year figure of $31,746.03, which appears as year two's DEP.

DEP1=31,746.03×9.512=25,132.28\begin{aligned} \text{DEP}_1 &= 31{,}746.03 \times \tfrac{9.5}{12} \\ &= 25{,}132.28 \end{aligned}
M01 = 3.5: from mid-March, 9.5 of the year's 12 months.

Read it as two facts wearing one number: the integer is which month, the decimal is how deep into it. If M01 is left at its default of 1.00, the worksheet assumes a January 1st start with no proration, which silently changes the year-one figure whenever the real problem describes a mid-year start.

Year and salvage order

LIF, M01, CST, SAL, YR is a fixed order: fields can be skipped past, never reordered. A zero-salvage problem just means pressing down through SAL without typing anything.

YR must be a positive integer; a fractional or negative year throws Error 4. DEP, RBV and RDV only compute for whole years relative to M01, never a partial year beyond that initial pro-rated first one.

DEP, RBV and RDV are read-only: typing a number while one is displayed does nothing. To change the year, scroll back to YR first, which is the mechanic the schedule-building section below relies on.

Declining balance and the DB percent

DB and its DBX cousin both need one extra input SL and SYD skip: the declining-balance percentage. Answer-first: press 2ND [SET] until DB or DBX appears, key in the percent (200 for double declining balance), press ENTER, then continue to LIF.

The default DB/DBX percentage is 200: twice the straight-line rate applied to remaining book value each year. Override it if needed: 150 gives 150%-declining balance, common in some tax contexts. The value must be positive; zero or negative throws Error 4.

DEPt=RBVt−1×DB%LIF\text{DEP}_t = \text{RBV}_{t-1} \times \frac{\text{DB}\%}{\text{LIF}}
Declining balance: 200% of the straight-line rate on what is left, never below salvage.

LIF must be a positive integer for DB, DBX and SYD, unlike straight-line, where a fractional life such as 31.5 years is allowed. A fractional life on DB or SYD throws Error 4 rather than rounding silently.

  1. 2ND [DEPR], then 2ND [SET] until DB (or DBX) appears
  2. Type the percentage, or ENTER to accept the 200 default
  3. ↓, enter LIF, M01, CST and SAL in order, ENTER after each
  4. ↓ to YR, leave at 1 or enter the year needed
  5. ↓ three times for DEP, RBV, RDV

DBX and the crossover

DBX matches DB in year one (same percentage, same math) but recalculates a straight-line alternative on remaining book value each year after. The moment straight-line beats continuing to decline, DBX switches over automatically.

This crossover is a real accounting device: pure declining balance never quite reaches zero on its own, so something must close the remainder eventually. DB alone leaves that gap; DBX closes it.

If a problem wants "pure" declining balance with no switch, confirm DB rather than DBX is selected: the two match in early years and only diverge at the crossover point, which makes a wrong selection easy to miss.

SYD is a real built-in method

SYD gets less attention than SL and DB but is a genuine option, not a workaround. Select it via 2ND [SET], and the input order matches straight-line: LIF, M01, CST, SAL, YR.

There's no percentage to enter; the worksheet derives the years'-digits fraction internally from LIF and the current year. Like DB, SYD requires LIF to be a positive integer.

SYD front-loads depreciation more aggressively than straight-line but less than 200%-declining balance in most cases, a useful second accelerated-method check when a DB answer looks off.

Reading DEP, RBV and RDV for any year

DEP, RBV and RDV are the last three fields, computed in fixed order once YR is set. Answer-first: DEP is the year's expense, RBV is book value remaining after that charge, RDV is depreciable value still left to write off.

RBV and RDV are equal whenever salvage is zero, since remaining book value and remaining depreciable value are then the same number. They diverge once SAL exceeds zero: RBV never drops below SAL, while RDV reaches exactly zero in the final depreciable year.

A small asterisk marker confirms a value is calculator-computed, not manually typed, useful when it's unclear whether DEP was overwritten.

Building a full schedule

Generating year two, three or beyond means scrolling from RDV back to YR, pressing CPT to add one, then scrolling back down through DEP, RBV and RDV to recompute. LIF, M01, CST and SAL stay stored, so nothing needs re-entering.

  • From RDV, press ↓ once to return to YR
  • Press CPT to increment YR (2.00, 3.00, and so on)
  • Press ↓ three times to recompute DEP, RBV and RDV

The schedule is complete once RDV hits exactly zero; incrementing YR further just returns DEP = 0.00.

This same loop is how to spot a DBX crossover year: the year DEP under DBX stops matching plain DB is the year the calculator switched methods.

Error 2 and Error 4

Two error codes are specific to this worksheet. Error 4 (out of range) fires if the DB percent, LIF or YR is zero or negative, CST or SAL is negative, or M01 falls outside 1 to 13.

Error 2 (invalid argument) fires when SAL is entered greater than CST: the calculator treats that as impossible rather than computing a negative depreciable base.

For any other unexpected code, the full BA II Plus error messages guide covers every code from Error 1 to Error 8, including ones tied to the cash flow and bond worksheets.

Switch methods in the chart at the top to see how each schedule bends

Is the worksheet faster than the formula? An honest test

For a single straight-line year, the formula wins. (Cost minus salvage) divided by life is one division: five seconds. Opening DEPR and keying LIF, M01, CST, SAL and YR takes fifteen to twenty seconds even at a comfortable pace.

DEP=CST−SALLIF\text{DEP} = \frac{\text{CST} - \text{SAL}}{\text{LIF}}
Straight-line, one full year: (cost − salvage) ÷ life.

The worksheet earns its keep on a multi-year schedule, especially declining balance or SYD. Hand-computing years two through five means recalculating a remaining base or digit fraction each time, easy to drop a term. The worksheet does that exactly, then lets you increment YR and read three numbers per year. The formula wins a sprint; the worksheet wins a schedule.

For CFA purposes this matters less than it sounds. Under the 2027 curriculum, FSA questions usually test whether accelerated versus straight-line changes net income and turnover across years, not whether a candidate can build a schedule under time pressure. Most vignettes hand over enough of the schedule already, tipping the balance toward the formula on exam day.

TaskFormula by handDEPR worksheet
Straight-line, one year, no proration~5 sec~15 sec
Straight-line, one year, with M01 proration~15 sec~18 sec
Declining balance, single year~10 sec~15 sec
Declining balance, five-year schedule~50-70 sec, rising error risk~35-45 sec, consistent
SYD, five-year schedule~60-80 sec, easy digit-sum slips~35-45 sec

When it actually pays off

The honest recommendation is narrow: learn DEPR if multi-year schedule questions specifically worry you, which shows up more in practice sets than the exam's own single-year item sets. If formula-only prep already works, there's no urgent need to add a worksheet close to an exam window. Learn the tool that fixes your weakness, not one that fills a gap you don't have.

It's worth the time for candidates who slip on multi-year arithmetic, or anyone comfortable with other worksheets (like the percent change worksheet or the breakeven worksheet), since DEPR uses the same 2ND [SET] / down-arrow / ENTER rhythm.

If the real question is whether to keep adding worksheets or switch approaches, the HP 12C for the CFA guide covers RPN entry, and the date worksheet guide covers another underused function for day-count problems.

Get every worksheet's exact keystrokes (DEPR, amortization, bond, cash flow and more) in one reference with the CFA Calculator Tips e-book, built around the BA II Plus for Level I and Level II candidates.

Questions people ask

These are the questions candidates search when DEPR stalls them mid-practice-set. Each answer leads with the direct fix, then the reasoning.

The two most common snags: picking the wrong method from the SET cycle, and mixing up what M01's decimal means. Both are covered above but deserve a direct answer here too.

If an issue isn't listed below, it's very likely an Error 2 or Error 4: check the error section above first, since most DEPR mistakes surface as one of those two rather than as a silently wrong number.

1Does the BA II Plus have a straight-line depreciation calculator built in?

Yes: press 2ND [DEPR], then 2ND [SET] until SL appears (usually already the default). Enter life, starting month, cost and salvage in that order, and DEP, RBV and RDV compute automatically as you scroll past YR.

This is the same worksheet used for all six methods, so "straight-line calculator" isn't a separate mode, just one option behind 2ND [SET].

Some candidates still prefer the plain formula, (cost minus salvage) divided by life, for a single year, reasonable given the timing comparison above.

2What does M01 mean on the BA II Plus depreciation worksheet?

M01 sets the month an asset enters service and how far into that month depreciation starts: the whole number is the month, 1 through 12, and the decimal is the fraction already elapsed before depreciation begins.

Enter 6.0 for an asset placed in service at the start of June, or 6.5 for one placed in service halfway through June. The calculator uses this to prorate the first year's charge, so a wrong M01 throws off year-one DEP even when everything else is right.

M01 must be at least 1 and below 13 or the calculator throws Error 4.